Following a major or intermediate overhaul, a crusher should undergo a no-load test run, typically lasting 2 to 6 hours, though the duration may be adjusted based on specific circumstances. Before starting, use a crane (if available) to rotate the eccentric shaft one full revolution; the machine may only be started once it is confirmed that there is no resistance. The no-load test run must meet the following requirements:
(1) Start-up and shut-down procedures must be followed, and all electrical interlocking systems must comply with maintenance specifications.
(2) All fasteners must be secure, with no signs of loosening.
(3) All lubrication points must be functioning properly, with no oil leaks.
(4) The temperature rise of the bearings must not exceed 30°C.
(5) The flywheel must rotate smoothly.
(6) All adjustment mechanisms must operate flexibly and function within their specified adjustment ranges.
Once the no-load test run is successfully completed, a load test run should be conducted, typically lasting 2 to 3 days (48 to 72 hours). The load test run must meet the following requirements:
(1) The crusher must not produce any periodic or significant impact noises.
(2) The temperature rise of the bearings must not exceed 40°C.
(3) The particle size of the crushed product (determined by the discharge opening gap) must meet the specified requirements.